SAFETY REMINDER :: NO Access to Construction Areas

Safety is a top priority at ICC! This is a reminder that employees, students, and visitors are prohibited from accessing ANY areas of the College marked as construction zones without prior authorization. For questions, please contact Director of Facilities Planning and Design Troy Hattermann at (309) 694-5156 or Facilities Manager Ryne Meardy at (309) 694-5121. 

Major Construction Update 8/28/15

  Listed below is an update of the major construction projects at ICC. East Peoria Campus: Roof Top Unit Replacement Phase 3 The Roof Top Unit Replacement Phase 3 is complete. Some adjustments and air balancing will continue into next month. Library Entrance Renovations The Library front entrance renovations are nearly complete. The final casework…  read more

Intersection by Dirksen Hall Closed for Asphalt Replacement

On Friday, August 7, the intersection at Centennial Dr. and Lakeside Dr. (by Dirksen Hall) will be closed for asphalt replacement. Demo work will occur on Friday, and new asphalt will be installed on Monday, August 10. The intersection will re-open on Tuesday, August 11. Submitted by Tom Braun, building and grounds supervisor.

Construction Update: Academic Support Services relocating (North Campus)

Academic Support Services (Library, Learning Lab, and the Studio) on the North Campus is currently in the process of moving from Cedar Hall to its new location in Arbor Hall on the west end of the ground floor by the elevator (Room A012). During this transition, there may be some minor interruptions of service, however…  read more

Arbor Drive and Parking Construction (North Campus)

Construction work on the Arbor Drive and parking has begun and is expected to be completed within a month. Please note: The Arbor Hall front entrance doors by the flagpole, as well as the front drive will be closed during construction. The project consists of replacing the driveway, adding sidewalks, and constructing a few parking…  read more

Construction UPDATES for the week of June 1

Here is an update on the major construction projects occurring around ICC campuses during the week of June 1: East Peoria Campus: Roof Replacement Phase 4 Roofing will be replaced above Rooms 307 and 308. The final gravel coating and roof caps will be installed over Rooms 323, 324, 325 and 326. The roof replacement…  read more

Construction Update: Corridor Closures begin May 13 (East Peoria and North Campuses)

During the summer months, major construction projects are scheduled on the East Peoria and North Campuses. In preparation for the work, several corridors adjacent to the construction will be closed to access beginning Wednesday, May 13. During the closures, corridors may initially be used for storage of construction equipment. As the work on the projects…  read more