Major Construction Update 8/28/15

 

Listed below is an update of the major construction projects at ICC.

East Peoria Campus:

Roof Top Unit Replacement Phase 3

  • The Roof Top Unit Replacement Phase 3 is complete.
  • Some adjustments and air balancing will continue into next month.

Library Entrance Renovations

  • The Library front entrance renovations are nearly complete.
  • The final casework items will be installed September 2.
  • The computer lab computers should arrive by the end of September.
  • Some punch list items are to be completed by September 2.

Library Carpet Replacement

  • The replacement of the Library carpeting is complete.

Restroom Renovations

  • The women’s and men’s restrooms – Rooms 201, 301, 214 and 314 — are open and usable.
  • Some adjustments in the restrooms are still in process.

Science Lab Phase 9

  • The student tables are scheduled to arrive the first week in September.
  • Some punch list items are to be completed by September 4.

North Campus:

Student Resource Center

  • Progress of the sheet pile driving has been slow due to the hard, dry ground. Work should be complete by September 1.
  • Student Resource Center lower level excavation will occur September 1 through September 3.
  • A temporary walkway between Arbor and Poplar Hall is in place.
  • The next phase of the project in September includes installation of footings and the lower lever concrete floor.

Arbor South Wing Demo

  • Work is complete with the Arbor South demo of the interior walls and floor.

Arbor Hall Drive and Parking

  • The North Campus Arbor Hall Drive and Parking is complete.
  • The storm water detention area has been installed.
  • The storm water detention area will be reseeded in the next week.

Submitted by Kevin Roberts, director of construction management.