Corridor and Classroom Renovation Project UPDATE (10/03/14)

This information is meant to give you a quick update on the Corridor and Classroom Renovation Project.  If you have a question regarding the information, contact the Facilities Call Center at Ext. 1888, Jason Dally Ext. 5454 or Kevin Roberts at Ext. 6838.

The Project Description can be reviewed on the August 29 update. This project will continue from the present into the winter months. Please watch for barricades and wet paint signs.

This Week’s Activities

  • Painting was completed in the Academic Building corridor from Rooms 207 to 211 and Rooms 238 to 240.
  • Corridor painting was completed in Academic Building corridor from Rooms 120 to 124.
  • Three quarters of the ceiling installation was completed in the Academic Building corridor from Rooms 207 to 211.
  • Ceiling installation was completed in Academic Building Rooms 120 to 129.
  • Carpeting was installed in Academic Building Rooms 234 to 240.
  • Carpeting was installed in Academic Building Rooms 207 to 210.
  • Carpeting was installed in Classrooms 218B and 219A.

 Next Week’s Activities

  • Ceilings will be installed in Academic Building Rooms 130 to 136.
  • Corridors near Academic Building Rooms 125 to 132 will be painted.
  • Classrooms 217B, 219B, 226A and 230A will be carpeted.
  • Carpeting will be installed in the Academic Building corridor by Room 211.
  • Ceramic tile will be removed in Academic Building Rooms 120, 123 and 127.
  • Carpeting will be installed in Academic Building Rooms 120 to 125.

 Future Tasks and Target Completion Dates

  • Academic Building second floor corridors – 10/3/2014
  • Academic Building first floor corridors – 10/24/2014
  • Academic Building cafeteria seating – 11/3 to 11/14/2014
  • Academic & Edwards Buildings Atrium, Bookstore to second floor east corridor – 10/20 to 10/31/2014
  • Academic Building (28) classrooms – 1/12/2015
  • Academic Building third floor corridors – 1/25/2015
  • Academic & Edwards Library entrance and third floor bridges to east corridor – 1/25 to 1/31/2015

Information provided by Director of Construction Management Kevin Roberts.