Faculty & Staff

Construction Update :: July 24, 2015

East Peoria Campus

Roof Replacement Phase 4

  • The roof replacement phase 4 is complete.

Roof Top Unit Replacement Phase 3

  • The Roof Top Unit Replacement Phase 3 is complete.
  • Some adjustments and air balancing will occur during the week of July 27.

Library Entrance Renovations

  • The glass walls are being installed.
  • The casework will be delivered and installed the week of July 27.
  • The computer lab ceiling grid is in place.
  • The new Library entrance is scheduled to open the week of August 3.

Library Carpet Replacement

  • The Library Entrance carpet is installed.
  • The circulation desk will be removed on August 3.
  • Carpeting on and under the Library spiral stair will be installed the week of August 3.
  • The Library will be open during normal business hours.

Restroom Renovations

  • Women’s and men’s restrooms at Academic Building Rooms 201, 301, have tile installed.
  • Installation of fixtures and partitions in restrooms 201 and 301 will occur the week of July 27.
  • Construction of wall finishes in restrooms 214 and 314 will occur the week of July 27.

Science Lab Phase 9

  • The casework has arrived and is being installed.
  • The floor tile will be installed next week.
  • The counter tops and student tables will arrive by July 30.
  • The science lab in Room 318E is scheduled to be complete by August 3.

North Campus

Student Resource Center

  • The sanitary sewer line has been installed to the new building site, which includes Maple and Poplar Hall.
  • The sheet pile driving will begin the week of July 27, and will last about three weeks.
  • Some excavating of the Student Resource Center will take place in the next few weeks.
  • A temporary walkway between Arbor and Poplar Hall will be placed before August 17.

Arbor South Wing Demo

  • Work is complete with the Arbor South demo of the interior walls and floor.

Arbor Hall Drive and Parking

  • The concrete work for the sidewalks, drive and parking space is complete.
  • Landscaping of the Arbor drive and parking will begin next week.

Submitted by Director of Construction Management Kevin Roberts.