Current Projects and Updates

Construction Maps

Project Updates

Status 6/13/2017

Elm (Student Center)

  • Summary of Upgrade – 33,957 Sq. Ft facility to support the provided services to the future students once ICC Peoria Campus renovations are complete.
  • Landscaper wants to push back planting until fall due to heat and n shade on plants and grasses
    • Project period April 1, 2015 to January 2016
    • Substantial Completion – January 2016
    • Project Complete

Birch Hall (Health Careers)

  • Summary of Upgrade – 21,127 Sq. Ft. facility to relocate a portion of the Health Careers Program downtown to the Peoria Campus
  • Brick staining to be scheduled
  • Trim between glass walls installed
    • Project period June 1 2016 to June 30 2017
    • Substantial Completion – March 1 2017
    • Project Complete

Cedar Hall (Health Careers)

  • Summary of Upgrade – 57, 479 Sq. Ft. facility to relocate the remainder of the Health careers Programs downtown to the Peoria Campus.
  • Substantial completion set for June 14th
  • Landscaping ongoing
  • Ambulance bay floor to be sealed week of June 19th
  • Furniture to be delivered June 26th and 27th with instillation starting July 5th
    • Project period April 4 2016 to June 30 2017
    • Substantial Completion – June 14 2017
      • ON TARGET

Altorfer Training Center

  • Summary of Upgrade – convert existing storage space into a training classroom and offices and constructing a new storage building.
  • New building is being enclosed
  • Painting complete
  • Data rack switch to take place June 29th
  • Concrete apron to be poured week of June 19th
    • Project period March 13, 2017 to June 2017
    • Substantial Completion – June 23 2017

Roof Replacement Phase 5

  • Summary of Upgrade – Replacement of the old air handler units 1-4
  • Phase 1 is 95% complete
  • First floor to be finished up week of June 12th
  • Phase 2 demolition is beginning
  • Work in mail room to take place after 4:30 pm week of June 19th
    • Project period May 16 2017 to July 2017
    • RTU replacement is scheduled for Saturday July 15th
    • Substantial Completion – July 21 2017

Roof Replacement Phase 6

  • Summary of Upgrade – Replacement of the old roof with a cold asphalt membrane insulation roof system
  • Tear off and roof replacement is ongoing
  • Condensate line needs replaced on all RTU’s. Current line causing leaks due to lip on connection
    • Project period March 16 2017 to July 2017
    • Substantial Completion – August 3 2017

Restroom Renovation Phase B2-PAC

  • Summary of Upgrade – Renovation Tower 39 Restrooms and PAC Restrooms
  • ACAD bathrooms drywall finished. Paint to follow
  • Tile to start June 26th on second floor
  • New plumbing lines ran
  • Floor leveled and block wall prepped for tile
    • Project period May 16 2017 to July 2017
    • Substantial Completion – July 21 2017

East Peoria Campus Roadway Replacement Phase 1

  • Summary of Upgrade-Reconstructing Dingledine Drive and part of College Drive
  • Milling of existing road complete
    • Project period June 6-July 5 2017
    • Substantial Completion – July 5 2017